Waterline
to impact traffic flow
by Brian DiTullio
CAREFREE
– A new waterline is set to cross Tom Darlington Drive that,
when completed, will improve service to the southern end of
town.
Traffic
flow will be affected on Tom Darlington for about seven to
10 days, according to Stan Francom, manager of Carefree Water
Co.
Construction
is scheduled to begin March 19. Traffic will be reduced to
one lane northbound and possibly diverted to the southbound,
west side of the divided roadway when necessary.
Town
council approved Phase II of Carefree’s 10‑inch waterline
extension project at its March 6 meeting. This portion of
the pipeline will extend from Tom Darlington at The Boulders
to the Languid Lane area in the Black Mountain foothills.
Francom
said last Thursday the new line will allow the area to have
“fire flow” water pressure, ranging from 60 to 80 pounds per
square inch.
“You’ll
be able to get about 1,550 gallons per minute at about 75
psi,” Francom told The Desert Advocate. “We could go higher,
but that’s downhill and we don’t want to blow the system out.”
The
Phase II contract is set for completion in 80 days. Should
the project take longer, Francom said the contractor would
be assessed $1,000 a day penalty for each day beyond the 80‑day
time period, unless an extension is granted.
Reasons
for an extension would include missed work days due to bad
weather, “extraordinary circumstances,” or if the project
is held up by an excessive amount of hard rock.
The
chances of the project being delayed due to major excavation,
or to adjust the pipeline’s alignment, is what council focused
on.
The
contract, awarded to Blucor Contracting Inc. for $318,474,
includes a rate of $430 an hour for hard‑rock excavation,
but that cost is not reflected in the bid–the reason being,
according to Francom, the project may not require any excavation.
“It
could be nothing; it could be $40,000,” said Francom at the
meeting, adding the uncertainty is the reason for the “rock
clause” in the contract.
Phase
I of the project extended the line from Stagecoach Pass at
Mule Train Road through The
Boulders to Tom Darlington Drive. Phase III is designed to
extend the 10‑inch waterline through the rest of the
Black Mountain foothills to connect with Carefree residents
within the
Cave Creek Water Company area of service.
“They’re
Carefree residents, but they’re on Cave Creek water,” said
Francom about Phase III. “This will make sure our residents
have good water flow.”
The
pipeline originates at the water storage tank at the corner
of Pima Road and Stagecoach Pass.