|
Bidders
await decision on wastewater treatment plant
by Brian DiTullio
CAVE CREEK - Water in, sewage out. That's the plan being
laid out in Cave Creek as the town continues its march toward
a modern, effective infrastructure.
According to town council, the new wastewater treatment
plant, to be called the "Cave Creek Water Ranch,"
is moving forward as planned. A selection committee is now
in the process of interviewing three engineering/contracting
firms, the finalists in the initial bid process.
To finance construction, the town has allocated about $25
million of the $50 million in revenue bonds or Water Infrastructure
Finance Authority loan proceeds approved by voters in 2005.
The town will use $17.5 million of the financing toward
the purchase of Cave Creek Water Company, approved at the
March 5 town council meeting.
The new plant will sit on a 76.45 acre parcel on the north
side of Carefree Highway at 44th Street, purchased last
December from the State Land Department for $4.275 million.
The town was the only bidder for the land.
With the site in hand, Cave Creek solicited contractors
to bid on the project and the finalists, according to Assistant
Town Engineer Souren Naradikian, are CH2M Hill, PCL Construction
Leaders, and Garey Construction, all with offices in the
metro Phoenix area.
The
three companies submitted final bids to a technical advisory
team on March 16. The team will choose the winning bidder
on March 27, subject to final approval by town council at
a subsequent meeting. The treatment plant is estimated to
cost around $20 million, Naridikian related, but final bid
numbers are not yet available.
Town council stipulated the winning bidder will be required
to operate the plant for at least two years so the town
can be "assured that the plant performs as designed
and it meets all Town requirements, those being that the
plant does not generate any intrusive noise or odor and
has aesthetic appearance that blends in with the character
of the Cave Creek community."
The new treatment plant will have a capacity of about 500,000
gallons per day, about double what the existing plant can
handle. It will also have the capability of being expanded
up to 3 million gallons per day.
Once the new plant is online, the existing Rancho Manana
plant will be decommissioned and torn down-sometime in 2009,
according to Naradikian. There will be no interruptions
of service while the new plant and sewer lines are connected,
nor will there be any disruptions when the old plant is
deactivated.
Naradikian points out that shutting down the old plant is
a very technical process that will involve the U.S. Environmental
Protection Agency. He also related both plants will be operated
simultaneously until it is proven the new plant operates
according to specifications.
"We won't shut down the old plant until we can prove
the new plant is working properly," said Naradikian.
Mayor Vincent Francia said once the old treatment plant
is gone, it will be up to the community to decide what to
do with the land.
"We haven't discussed it yet, but selling it to a developer
is certainly an option," said Francia.
Several subdivisions in the Cave Creek area already have
"dry" sewer connections, i.e. the necessary lines
were put in during construction and all that is required
is for the houses to be connected to the new system.
|