DeWitt
said members of the public typically ask three questions concerning
new projects, beginning with: Why it is needed? For the past
several years, the peak Valley electrical load has met or exceeded
growth projections and is expected to increase four percent
each year through 2014.
Residents
also ask about the route. “There isn’t any power line that you
can site that doesn’t have impacts,” DeWitt pointed out. An
environmental consulting firm analyzes factors such as existing
and planned land uses, landscape views, historic and archaeological
features, and plant and wildlife species. The analysis is still
under review.
The
siting team is looking to combine the benefits of a previously
certificated North Valley 230kV project in the same area with
the proposed one. In other words, one structure could support
two lines. Both corridors begin near the Raceway substation
in Peoria north of Carefree Highway, travel east along the Dove
Valley Road alignment and turn southeast approaching I‑17.
Both will end at the Pinnacle Peak substation near Scottsdale,
but the route east of I‑17 may vary.
Preliminary
plans suggest several alternatives for navigating through the
north Phoenix area roughly bounded by 27th Avenue and Seventh
Street and south of Pinnacle Peak Road north past Patton Road.
“Those are the areas that have seen the most amount of change
in the study area,” DeWitt explained. Most of the remaining
land remains vacant.
The
final public question DeWitt typically hears relates to structure
design. The double‑
circuit
steel monopole structures will stand between 130 feet and 150
feet tall and sport two
triangular‑shaped
conductors. APS will space the poles approximately 600‑800
feet apart.
DeWitt
announced at the meeting that APS was ready to mail 48,000 newsletters
providing a project overview to residents in the affected areas.
To further communicate with the public, APS will hold two informational
open houses April 25 and 26 from 6 to 8 p.m. to answer remaining
questions and collect feedback. The meetings will be held at
the Goelet A.C. Beuf Community Center, 3435 W. Pinnacle Peak
Road.
APS
anticipates finishing the outreach component of the project
by this summer. Information detailing the project’s needs, description,
cost, environmental issues and outreach efforts will go into
an application for a Certificate of Environmental Compatibility
filed with the Arizona Corporation Commission, which must approve
the final route.
During
the last five years, APS has successfully sited and received
ACC approval for more than 150 miles of new high‑voltage
power lines and seven substations. The new line will be in service
by 2010.
For
more information, call (602) 493‑4446 or go to http://siting.aps.com.
Reach
the reporter at ambria@thedesertadvocate.com.