Cave
Creek sewer plant: $31 million
Construction
could begin as early as May
by
Brian DiTullio
CAVE
CREEK – Building a new wastewater treatment plant will
consist of two phases and could cost as much as $31.1
million.
Proposed
numbers and construction schedules were unveiled to town
council at a work session on July 16. Garney Construction
was chosen by a technical advisory team as the construction
contractor, and the firm Burns & McDonnell was selected
as design engineers. American Water Co. will operate the
current plant until its demolition.
Al
Dreska, senior program director for Parsons, an engineering
and construction firm, gave a
detailed PowerPoint presentation about the project, which
has been in the town’s plans for several years.
The
proposed financials included a “Guaranteed Maximum Price”
of $31,103,288 for the entire project, which includes
design, construction, and operation for the first two
years. Phase I, the design phase, is estimated to cost
$4,345,431. That contract will be presented to town council
at its Aug. 20 meeting for review and possible approval.
Actual
construction costs are estimated to be $23,306,598.
No
date for approval of that contract has been set. The overall
proposed schedule shows construction beginning in May
2008, with completion scheduled for August 2009.
Town
Manager Usama Abujbarah pointed out to council that a
Water Infrastructure Finance Authority loan would cover
only construction costs, not the cost of operating the
plants, estimated to be just under $4 million for the
next four years.
“We
have to fund the operations,” Abujbarah said. “WIFA won’t
do it.”
The
new treatment plant, called the Cave Creek Water Ranch,
will be located near the northeast corner of 44th Street
and Carefree Highway. The facility is to be built below
grade, with the idea that it won’t be easily visible from
nearby roadways. The project includes noise reduction
measures and odor control.
Bob
Schulz with Burns & McDonnell noted this is a fairly
“sizable” project for Cave Creek and that his company
would do its best to blend the facility into the landscape.
Tom
Auay‑Fuay, introduced as the lead project manager,
informed the council that about 120 people would be involved
in the plant’s construction.
The
facility is being designed to handle 750,000 gallons of
waste‑water per day, with the ability to double
capacity in the future, should development require it.
The engineers said the plant would have at least a 25‑year
life span, but probably much longer than that.
Town
Engineer Wayne Anderson said he doesn’t expect to have
to double the plant’s capacity until at least 2020.
Mayor
Vincent Francia asked about creating a community garden
on some of the unused acreage of the site, to which Schulz
replied they would have to check the kinds of chemicals
employed in the treatment process, as the treated effluent
is being used mainly for irrigation purposes at Rancho
Manana golf course.
The
existing wastewater treatment plant will be decommissioned
and torn down about two years after the new plant begins
operation. According to Abujbarah, the town has not decided
what it will do with that property, but is considering
auctioning it off and putting the revenue back into the
cost of building and operating the new plant. The current
plant site has not yet been appraised.
Since
the meeting was a work session, no formal actions were
taken.