Council
approves contract to design sewer treatment plant
$4.3
million contract first part of total $31.6 million cost
by
Brian DiTullio
CAVE
CREEK – Town council at its Monday meeting approved the
overall contract for the construction
of a new wastewater treatment plant, including the funding
for the design phase.
Council
received a presentation, recapping a work session earlier
this summer on the proposed
cost to design, build and operate the new wastewater treatment
plant. Phase 1, the only
phase approved for funding, will cost $4,343,431. This
includes the design and pre‑construction
costs, operating the existing plant for two years and
a $250,000 town‑controlled contingency.
Most
of the funding will come from a Water Infrastructure Finance
Authority loan, according to Al Drescha, one of the design
engineer consultants. The only costs not covered by WIFA
are the plant operations, estimated to be $542,904 for
Phase 1.
Drescha
said they have worked out a two‑year time line,
with design planning beginning next month and completion
and permitting completed by July 2008. Pipeline construction
would begin in April 2008, and the entire project would
be finished in September 2009.
The
plant is estimated to cost $24.8 million to construct.
Total costs, including plant operations, all design costs
and an additional town‑controlled contingency of
$1.75 million, added up to $31.6 million. However, approximately
$2.2 million of that cost is for operations, which wouldn’t
be covered by the WIFA loan.
Later
on in the meeting, council approved the application of
a $26.1 million WIFA loan to cover the rest of construction
and design costs for the new treatment plant.
Approval
of financing for Phase 2, plant construction, would happen
no later than July 2008, according to Drescha, once again
stressing the council only is funding Phase one at this
point.
Drescha
also explained the town‑controlled contingency money
is under the complete control of Cave Creek and Town Manager
Usama Abujbarah to fund any changes the town deems necessary.
This money is not for the contractor to spend or request.
The
measure passed by unanimous vote.
The
town now has borrowed more than $50 million from WIFA,
according to council meeting minutes and agendas. Including
the $26.1 million loan for the treatment plant on Aug.
20, the town also borrowed $20.1 million to purchase Cave
Creek Water Company this past spring, $6.6 million to
purchase and make improvements to Desert Hills Water Company
during the last year, and more than $6 million to purchase
the land for the new treatment plant.
According
to Town Accountant Marian Groeneveld, approximately $6.6
million of the monies borrowed have not been spent and
will be used toward the design of the new treatment plant
and water system improvements.
However,
the numbers show a shortfall of about $2.6 million between
funds on hand and projects
approved. Groeneveld said the town would be meeting with
WIFA in the near future to discuss how to close this gap.